32.
Commissioners Court - Regular Session
- Meeting Date:
- 04/25/2023
- Title:
- Smith Contracting 22IFB131 CO2 SGRR & Remuda
- Submitted For:
- Robert Daigh
- Submitted By:
- Vicky Edwards, Infrastructure
- Department:
- Infrastructure
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action on Change Order No 2 to contract number 22IFB131 for Smith Contracting Co, Inc. in the amount of -$145,724.56 for San Gabriel Ranch Road and Remuda Drive Improvements. Funding source: P492
Background
This Change Order is a balancing Change Order. All work has been completed. The original contract amount was $2,072,461.30. With the addition of Change Order No 1 in the amount of $36,869.17 and this Change Order No 2 for -$145,724.56, the final contract amount will be $1,963,605.91.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 04/19/2023 01:58 PM |
- Form Started By:
- Vicky Edwards
- Started On:
- 04/17/2023 10:56 AM
- Final Approval Date:
- 04/19/2023