Discuss, consider and take appropriate action on Change Order No 1 to contract number 22IFB127 for Cash Construction in the amount of $73,520.80 for Cross Culvert Replacements. Funding source: 01.0200.0210.003599.
Background
This Change Order is a balancing Change Order. All work has been completed. The original contract amount was $1,751,359.00. With the addition of this Change Order in the amount of $73,520.80, the final contract amount will be $1,824,879.80.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Hal Hawes | Hal Hawes | 05/16/2023 09:59 AM |
| County Judge Exec Asst. | Becky Pruitt | 05/17/2023 09:55 AM |
- Form Started By:
- Vicky Edwards
- Started On:
- 05/16/2023 09:33 AM
- Final Approval Date:
- 05/17/2023