28.
Commissioners Court - Regular Session
- Meeting Date:
- 07/18/2023
- Title:
- ESOC Ops Floor Console (P625) – Vaughn Change Order 1
- Submitted For:
- Dale Butler
- Submitted By:
- Wendy Danzo, Facilities Management
- Department:
- Facilities Management
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action on accepting a report from Vaughn Construction, LLC, Change Order No. 1 for the Williamson County ESOC Ops Floor Console project (P625) for a time only change of 25 days toward substantial completion. Funding Source is P625
Background
This change order is for various changes requested by Williamson County. This is a $0, time only change increasing substantial completion by 25 days for a July 26, 2023 completion date. Department point of contact is Angel Gomez, Sr. Project Manager for Facilities Management. On March 22, 2022, the Williamson County Commissioners Court approved Williamson County Architect, Trenton Jacobs, with authority to approve change orders under Local Government Code Sec. 262.031, in relation to Williamson County construction and facilities projects. This report is being provided for purposes of notifying the court of such change order and to place it in the minutes of the Commissioners Court. Funding for this project will be P625.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Hal Hawes | Hal Hawes | 07/11/2023 11:14 AM |
| County Judge Exec Asst. | Becky Pruitt | 07/12/2023 10:28 AM |
- Form Started By:
- wendy.danzoy
- Started On:
- 07/11/2023 11:01 AM
- Final Approval Date:
- 07/12/2023