Commissioners Court - Regular Session
- Meeting Date:
- 08/15/2023
- Title:
- ESOC Operations Floor Consoles (P625) – Vaughn Change Order 2
- Submitted For:
- Dale Butler
- Submitted By:
- Wendy Danzo, Facilities Management
- Department:
- Facilities Management
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action on accepting a report from J. T. Vaughn Construction, Change Order No. 2 for the ESOC Operations Floor Consoles project (P625) for a time extension of 55 days. Funding Source is P625.
Background
This change order is for time only for 55 days due to changes in scope requested by County. There is no increase in funds. New substantial completion date will be September 19, 2023. Department point of contact is Angel Gomez, Facilities Management Project Manager. On March 22, 2022, the Williamson County Commissioners Court approved Williamson County Architect, Trenton Jacobs, with authority to approve change orders under Local Government Code Sec. 262.031, in relation to Williamson County construction and facilities projects. This report is being provided for purposes of notifying the court of such change order and to place it in the minutes of the Commissioners Court. Funding for this project is P625.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Hal Hawes | Hal Hawes | 08/08/2023 09:59 AM |
| Facilities Management | wendy.danzoy | 08/08/2023 01:29 PM |
| Hal Hawes | Hal Hawes | 08/08/2023 03:31 PM |
| County Judge Exec Asst. | Becky Pruitt | 08/08/2023 04:01 PM |
- Form Started By:
- wendy.danzoy
- Started On:
- 08/07/2023 01:41 PM
- Final Approval Date:
- 08/08/2023