44.
Commissioners Court - Regular Session
- Meeting Date:
- 08/22/2023
- Title:
- 22IFB39 - CR 111 Westinghouse Rd Change Order #11 (City of Georgetown WL)
- Submitted By:
- Julissa Vasquez, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 11 in the amount of $81,433.12 for Project 22IFB39 CR 111 Westinghouse Rd (Capital Excavation) P: 292 Funding Source: Road Bond.
Background
This Change Order provides compensation to Contractor for relocating a City of Georgetown water line that is in conflict with the proposed driveway culvert. Please see attached Change Order for additional information.
This Change Order results in an increase of $81,433.12 to the Contract amount, for an adjusted Contract total of $22,244,981.80. The original Contract amount was $21,024,332.88. As a result of this and previous Change Orders, $1,220,648.92 has been added to the Contract, resulting in a 5.81% increase in the Contract cost. As a result of this Change Order, zero (0) days will be added to the Contract.
This Change Order results in an increase of $81,433.12 to the Contract amount, for an adjusted Contract total of $22,244,981.80. The original Contract amount was $21,024,332.88. As a result of this and previous Change Orders, $1,220,648.92 has been added to the Contract, resulting in a 5.81% increase in the Contract cost. As a result of this Change Order, zero (0) days will be added to the Contract.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 08/17/2023 07:38 AM |
- Form Started By:
- Julissa Romero
- Started On:
- 08/16/2023 12:38 PM
- Final Approval Date:
- 08/17/2023