Commissioners Court - Regular Session
- Meeting Date:
- 12/19/2023
- Title:
- Final plat for the Santa Rita Ranch Phase 6 Section 1 subdivision – Pct 2
- Submitted For:
- Robert Daigh
- Submitted By:
- Adam Boatright, Infrastructure
- Department:
- Infrastructure
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action on approval of the final plat for the Santa Rita Ranch Phase 6 Section 1 subdivision – Precinct 2.
Background
This is the first section of the Santa Rita Ranch Phase 6 development. It consists of 60 single family lots, 1 open space/landscape/utility lot and 2 open space/water quality/drainage/landscape/utility lots and 4,703 feet of new public roads. Roadway and drainage construction is not yet complete, but a performance bond in the amount of $6,067,890.25 has been posted with the County to cover the cost of the remaining construction.
Timeline
2023-09-20 – initial submittal of the final plat
2023-10-12 – 1st review complete with comments
2023-11-17 – 2nd submittal of final plat
2023-12-01 – 2nd review complete with minor comments
2023-12-04 – 3rd submittal of final plat
2023-12-13 – 3rd review complete with comments clear
2023-12-13 – receipt of final plat with signatures
2023-12-14 – final plat placed on the December 19, 2023 Commissioners Court agenda for consideration
Timeline
2023-09-20 – initial submittal of the final plat
2023-10-12 – 1st review complete with comments
2023-11-17 – 2nd submittal of final plat
2023-12-01 – 2nd review complete with minor comments
2023-12-04 – 3rd submittal of final plat
2023-12-13 – 3rd review complete with comments clear
2023-12-13 – receipt of final plat with signatures
2023-12-14 – final plat placed on the December 19, 2023 Commissioners Court agenda for consideration
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 12/14/2023 11:15 AM |
- Form Started By:
- Adam Boatright
- Started On:
- 12/14/2023 11:01 AM
- Final Approval Date:
- 12/14/2023