Skip to main content

AgendaQuick™

View Agenda Item

54.
Commissioners Court - Regular Session
Meeting Date:
05/07/2024
Title:
24IFB19 CR138 Right Turn Lane at SH130 - Change Order #1 (Additional Safety Measures)
Submitted By:
Julissa Vasquez, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 1 in the amount of $29,920.92 for Project 24IFB19 CR138 Right Turn Lane at SH130 (Smith Contracting) P: 463 Funding Source: Road Bond.

Background

This Change Order adds additional signs to the project to improve the safety along the roadway and updates the roadway street name signs from CR 138 to East WilCo Hwy. This Change Order also adds a pedestrian handrail to improve safety along a section of the shared use path with steep side slopes. 

Lastly, the Change Order adds a line item for law enforcement presence during nighttime lane closure operations at CR 138 and SH 130. Due to the amount of traffic and the location of the project, it was determined that this would be the safest most effective way to perform the final paving operation. Please see attached Change Order for additional information.

This Change Order results in a net increase of $29,920.92 to the Contract amount, for an adjusted Contract total of $1,778,859.67. The original Contract amount was $1,748,938.75.  As a result of this and all Change Orders to-date, $29,920.92 has been added to the Contract, resulting in an 1.71% net increase in the Contract cost.  No additional days will be added to or deducted from the Contract as a result of this Change Order. 


 

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Becky Pruitt 05/02/2024 09:08 AM
Form Started By:
Julissa Romero
Started On:
05/01/2024 10:26 AM
Final Approval Date:
05/02/2024