102.
Commissioners Court - Regular Session
- Meeting Date:
- 09/10/2024
- Title:
- 23IFB8 Corridor H - Sam Bass Road Change Order #4 (Walsh Pond)
- Submitted By:
- Julissa Vasquez, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 4 in the amount of $70,739.02 for Project 23IFB8 Corridor H - Sam Bass Road (Cash Construction) P: 462 Funding Source: Road Bond.
Background
This Change Order adds revised plan sheets and adjusts plan quantities for the proposed detention pond needed due to Parcel 60 acquisition not being finalized at the time of design. This Change Order also adds a new drainage item due to this redesign. Please see attached Change Order for additional details.
This Change Order results in a net increase of $70,739.02 to the Contract amount, for an adjusted Contract total of $33,884,393.16. The original Contract amount was $36,145,959.00. As a result of this and all Change Orders to-date, $2,261,565.84 has been deducted from the Contract, resulting in a 6.26% net decrease in the overall Contract cost. No time will be added to the Contract for this Change Order.
This Change Order results in a net increase of $70,739.02 to the Contract amount, for an adjusted Contract total of $33,884,393.16. The original Contract amount was $36,145,959.00. As a result of this and all Change Orders to-date, $2,261,565.84 has been deducted from the Contract, resulting in a 6.26% net decrease in the overall Contract cost. No time will be added to the Contract for this Change Order.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 09/05/2024 12:04 PM |
- Form Started By:
- Julissa Romero
- Started On:
- 08/30/2024 07:46 AM
- Final Approval Date:
- 09/05/2024