39.
Commissioners Court - Regular Session
- Meeting Date:
- 10/22/2024
- Title:
- Approval of the Guaranteed Maximum Price (GMP) 02 for the Justice Center Improvements with J.T. Vaughn Construction, LLC for Facilities Management
- Submitted For:
- Joy Simonton
- Submitted By:
- Johnny Grimaldo, Purchasing
- Department:
- Purchasing
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action on approving the Guaranteed Maximum Price Proposal (GMP) Bid Package 02 – Security Upgrades & Gym Renovations with awarded RFP #23RFP93 Construction Manager at Risk (CMAR) for the Justice Complex Improvements Project, J.T. Vaughn Construction, LLC, in the amount of Three Million Three Hundred Thirty Thousand Eight Hundred Thirty- Two Dollars ($3,330,832.00) and authorize the execution of the GMP02 between J.T. Vaughn Construction, LLC, and Williamson County. The funding source is P476.
Background
The guaranteed maximum price (GMP) Bid Package 02 – Security Upgrades & Gym Renovations is for the Justice Complex Improvements Project RFP #23RFP93 awarded on 05/07/2024 with agenda item #38, to perform the work approved on the above-mentioned project. Contract Audit and Legal have reviewed. The funding source is P476, Origination ID #1249, and the point of contact is Christy Matoska.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 10/17/2024 08:38 AM |
- Form Started By:
- Johnny Grimaldo
- Started On:
- 10/08/2024 12:39 PM
- Final Approval Date:
- 10/17/2024