22IFB57 CR 401 Reconstruction - Change Order #10 (Final Balancing)
Submitted By:
Julissa Vasquez, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 10 in the amount of ($1,842.48) for Project 22IFB57 CR 401 (James Construction Group) P: 390 Funding Source: Road Bond.
 

Background

This Change Order provides the final balancing for the overruns/underruns of Contract quantities on the project that are a result of addressing field conditions not accounted for in the original plans.

This Change Order results in a net decrease of $1,842.48 to the Contract amount, for an adjusted Contract total of $13,961,272.18. The original Contract amount was $12,673,200.94. As a result of this and all Change Orders to-date, $1,288,071.24 has been added to the Contract, resulting in a 10.16% net increase in the Contract cost. No additional days will be added to or deducted from the Contract as a result of this Change Order.
 

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Becky Pruitt 10/31/2024 08:50 AM
Form Started By:
Julissa Romero
Started On:
10/28/2024 06:58 AM
Final Approval Date:
10/31/2024