45.
Commissioners Court - Regular Session
- Meeting Date:
- 03/11/2025
- Title:
- 24IFB57 Ronald Reagan Blvd. Widening - Change Order #4 (Signal Pole)
- Submitted By:
- Julissa Vasquez, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 4 in the amount of $90,550.00 for Project 24IFB57 Ronald Reagan Blvd. Widening (Chasco Constructors) P: 336 Funding Source: Road Bond.
Background
This Change Order adds quantities and new items to match the traffic signal poles with the foundation types shown on the plans. In addition, it corrects traffic signal work quantities and missing items not included on the as-bid plan set. Multiple items will be added by this Change Order. Please see the attached Change Order for additional details.
This Change Order results in a net increase of $90,550.00 to the Contract amount, for an adjusted Contract total of $52,453,601.50. The original Contract amount was $52,159,299.00. As a result of this and all Change Orders to-date, $294,302.50 has been added to the Contract, resulting in a 0.56% net increase in the Contract cost. No additional days will be added to or deducted from the Contract as a result of this Change Order.
This Change Order results in a net increase of $90,550.00 to the Contract amount, for an adjusted Contract total of $52,453,601.50. The original Contract amount was $52,159,299.00. As a result of this and all Change Orders to-date, $294,302.50 has been added to the Contract, resulting in a 0.56% net increase in the Contract cost. No additional days will be added to or deducted from the Contract as a result of this Change Order.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Andrea Schiele | 03/06/2025 05:16 PM |
- Form Started By:
- Julissa Romero
- Started On:
- 03/05/2025 06:57 AM
- Final Approval Date:
- 03/06/2025