Commissioners Court - Regular Session
- Meeting Date:
- 06/17/2025
- Title:
- Final plat for the Santa Rita Ranch Phase 7B Section 3 subdivision – Pct 2
- Submitted For:
- Adam Boatright
- Submitted By:
- Adam Boatright, Infrastructure
- Department:
- Infrastructure
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action on approval of the final plat for the Santa Rita Ranch Phase 7B Section 3 subdivision – Precinct 2.
Background
This is the next section of the Santa Rita Ranch Phase 7B development. It consists of 37 single family lots, 2 open space/drainage/utility lots and 1,370 feet of new public roads. Roadway and drainage construction is not yet complete but a performance bond in the amount of $4,721,361.30 has been posted with the County to cover the remaining construction.
Timeline
2024-12-05 – initial submittal of the final plat
2025-01-04 – 1st review complete with comments
2025-04-08 – 2nd submittal of final plat
2025-04-21 – 2nd review complete with comments
2025-05-21 – 3rd submittal of final plat
2025-05-21 – 3rd review complete with comments clear
2025-06-06 – receipt of final plat with signatures
2025-06-12 – final plat placed on the June 17, 2025, Commissioners Court agenda for consideration
Timeline
2024-12-05 – initial submittal of the final plat
2025-01-04 – 1st review complete with comments
2025-04-08 – 2nd submittal of final plat
2025-04-21 – 2nd review complete with comments
2025-05-21 – 3rd submittal of final plat
2025-05-21 – 3rd review complete with comments clear
2025-06-06 – receipt of final plat with signatures
2025-06-12 – final plat placed on the June 17, 2025, Commissioners Court agenda for consideration
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Delia Colon | 06/12/2025 12:10 PM |
- Form Started By:
- Adam Boatright
- Started On:
- 06/12/2025 11:46 AM
- Final Approval Date:
- 06/12/2025