38.
Commissioners Court - Regular Session
- Meeting Date:
- 09/22/2026
- Title:
- Jail South Air Handler Unit (AHU) Replacement – Cleary Zimmermann Engineers, LLC – Supplemental Agreement No 2
- Submitted For:
- Dale Butler
- Submitted By:
- Gretchen Glenn, Facilities Management
- Department:
- Facilities Management
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider, and take appropriate action on approving the Supplemental Agreement No. 2 to the Professional Services Agreement for Design & Engineering Services between Williamson County and Cleary Zimmermann Engineers, LLC relating to the Williamson County Jail South Air Handler Unit (AHU) Replacement. Funding source is 01.0100.0509.004100.
Public Background
This Supplemental Agreement No 2 to the Professional Services Agreement for Design & Engineering Services between Williamson County and Cleary Zimmermann Engineers, LLC is for compensation pertaining to services outside the original scope of work. The supplemental services include revising construction documents to remove the phasing plan and providing an updated opinion of probable construction cost for the Jail S AHU Replacement. This agreement increases the previously supplemented contract amount by $4,500.00 and extends the service date through September 30, 2027.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
No file(s) attached.