Reimbursement of Contingency Funds
From:
Taro EchiburĂș, Director, Department of Community Services
Staff Contact:
Todd N. Riddiough, Principal Civil Engineer, Department of Community Services, x8039
Supervisorial District Impact:

Subject

Approve reimbursement of $51,555 to the Road Fund for FY 21/22 Quarter 1 activities for efforts to assemble construction ready documents, to pursue grant application opportunities, and implement construction of road projects and adopt budget resolution increasing appropriations and estimated revenues for the Road Fund by $51,555. (General fund impact $51,555) (4/5 vote required) (Echiburú/Riddiough)

Recommended Action

  1. Approve reimbursement of $51,555 to the Road Fund for FY 21/22 Quarter 1 activities for efforts to assemble construction ready documents, to pursue grant application opportunities, and implement construction of road projects; and
     
  2. Adopt a budget resolution increasing appropriations and estimated revenues for the Road Fund by $51,555 for reimbursement of project activities for FY 21/22 Quarter 1.

Strategic Plan Goal(s)

Safe Communities

Reason for Recommended Action/Background

In the Fiscal Year (FY) 21-22 Adopted Budget, the Board of Supervisors allocated $350,000 in contingency funds to the Department of Community Services for efforts to assemble construction ready documents, to pursue grant application opportunities, and implement construction of road projects.
 
For Quarter 1 of FY 21-22, County staff efforts of $51,555 were expended toward work on the following projects that are in process:
 
  • Ongoing design efforts on the 2022 Pavement Preservation Project
  • Ongoing design efforts on the County Road 27 Bike Lane & Rehabilitation Project
  • Ongoing design efforts and Cal Fire grant opportunity for the County Road 41 Washout Relocation Project
 
The attached budget resolution is needed to complete the $51,555 reimbursement to the Road Fund using the contingency funds. Such appropriations are authorized with a four-fifths vote of the Board of Supervisors pursuant to Government Code section 29125.

Collaborations (including Board advisory groups and external partner agencies)

County Administrator’s Office

Competitive Bid Process

N/A

Fiscal Impact

Fiscal impact (see budgetary detail below)

Fiscal Impact (Expenditure)

Total cost of recommended action:
$    51,555
Amount budgeted for expenditure:
$    0
Additional expenditure authority needed:
$    51,555
One-time commitment:
Yes

Source of Funds for this Expenditure

General Fund
$51,555

Further explanation as needed:

Shown in Adopted Budget FY21-22 Total Appropriation for Contingencies for “Roads” at $350,000. This is the first reimbursement request for FY21-22 efforts.

Attachments

Form Review

Inbox Reviewed By Date
Todd Riddiough (Originator) Todd Riddiough 12/23/2021 01:51 PM
Financial Services mpatterson 01/06/2022 01:09 PM
County Counsel Phil Pogledich 01/06/2022 01:10 PM
Form Started By:
Todd Riddiough
Started On:
12/20/2021 12:06 PM
Final Approval Date:
01/06/2022