Consent-Law & Justice Services # 21.
Board of Supervisors
Sheriff-Coroner/Public Administrator
- Meeting Date:
- 03/22/2022
- Brief Title
- Purchase of Fixed Asset Items for Animal Services
From:
Tom Lopez, Sheriff-Coroner-Public Administrator, Yolo County Sheriff's Office
Staff Contact:
Dale Johnson, Undersheriff, Sheriff’s Office, x5256
Supervisorial District Impact:
Subject
Adopt budget resolution to use Animal Services Trust fund balance to increase appropriations in the amount of $27,078 for the purchase of replacement equipment, and approve the amendment to the 2021-22 Authorized Equipment List for the purchase of the fixed assets. (No general fund impact) (4/5 vote required) (Lopez/Johnson)
Recommended Action
- Adopt budget resolution to use Animal Services Trust fund balance to increase appropriations for the purchase of replacement water softeners in the amount of $10,503 and a new automatic gate in the amount of $16,575; and
- Approve amendment to the FY 21-22 Authorized Equipment List allowing the purchase of the fixed assets.
Strategic Plan Goal(s)
![]() |
Safe Communities |
Reason for Recommended Action/Background
Yolo County, through the Sheriff’s Office Animal Services Section, is contractually responsible for providing all cities, unincorporated areas, and the campus of UCD with animal control ordinance enforcement, dog licensing, shelter operation and spay/neuter education services. In the past fiscal years, the Sheriff’s Office has contracted with the City of Davis, City of West Sacramento, City of Winters, City of Woodland, and UCD to receive reimbursement for these services, with the agreement that any unspent portion of annual payment resulting from unanticipated animal service savings will be placed in an "Animal Services Trust" for future shelter projects, animal services equipment, or replacement items.
Animal Services staff has identified an immediate need to replace two water softeners at the shelter. One unit in the laundry room is inefficient and outdated, and the one unit used in conjunction with the pressure washer system that cleans and sanitizes the kennels is currently outdated and inoperable. The water softeners are essential to keep several pieces of equipment at the shelter functioning properly by removing the minerals that cause scale buildup in pipes and appliances, reducing the maintenance needed on these items. The cost of replacement for the water softeners is $10,503. As one of the existing water softeners is leased and one is owned by the County, purchasing both units will also remove the need to continue the lease payment.
There is also an existing need to upgrade security features at the shelter. Staff proposes to replace the front access gate and side panels with an automated iron gate. The current fencing and main gates are chain link construction, aged, and do not provide adequate protection for staff or shelter animals. The fencing will match what is already in place at the Sheriff's Office and will create a secure, cohesive campus. The cost of the upgrade is $16,575.
Because these items are fixed assets, the Sheriff's Office is also requesting Board authority to amend the 2021-22 Authorized Equipment List.
Animal Services staff has identified an immediate need to replace two water softeners at the shelter. One unit in the laundry room is inefficient and outdated, and the one unit used in conjunction with the pressure washer system that cleans and sanitizes the kennels is currently outdated and inoperable. The water softeners are essential to keep several pieces of equipment at the shelter functioning properly by removing the minerals that cause scale buildup in pipes and appliances, reducing the maintenance needed on these items. The cost of replacement for the water softeners is $10,503. As one of the existing water softeners is leased and one is owned by the County, purchasing both units will also remove the need to continue the lease payment.
There is also an existing need to upgrade security features at the shelter. Staff proposes to replace the front access gate and side panels with an automated iron gate. The current fencing and main gates are chain link construction, aged, and do not provide adequate protection for staff or shelter animals. The fencing will match what is already in place at the Sheriff's Office and will create a secure, cohesive campus. The cost of the upgrade is $16,575.
Because these items are fixed assets, the Sheriff's Office is also requesting Board authority to amend the 2021-22 Authorized Equipment List.
Collaborations (including Board advisory groups and external partner agencies)
The contracted cities have been notified of these purchases and have not objected to the Sheriff's Office plan. County Counsel has approved the attached resolution as to form. Purchasing will assist with the procurement of the fixed assets.
Competitive Bid Process/Vendor Performance
A three bid process will be used to purchase any fixed asset items, excluding items that have pricing or service based on an existing Master Contract.
Fiscal Impact
No Fiscal Impact
Fiscal Impact (Expenditure)
- Total cost of recommended action:
- $ 27,078
- Amount budgeted for expenditure:
- $ 0
- Additional expenditure authority needed:
- $ 27,078
- One-time commitment:
- Yes
Source of Funds for this Expenditure
- Animal Services Trust
- $27,078
Further explanation as needed:
There is no associated cost to the County by approving the budget resolution and no General Fund or Public Safety Funds are required to purchase the fixed assets. The Animal Services Trust has sufficient funding to purchase the requested equipment. The Sheriff’s Office now requests approval of a budget resolution to move $27,078 from the trust to the Animal Services FY 2021-22 operating budget. $27,078 will be moved into the major object: Equipment.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Tom Lopez | Tom Lopez | 03/09/2022 03:41 PM |
| Financial Services | mpatterson | 03/11/2022 09:59 AM |
| County Counsel | Phil Pogledich | 03/11/2022 02:33 PM |
- Form Started By:
- Selena Hobbs
- Started On:
- 03/01/2022 11:48 AM
- Final Approval Date:
- 03/11/2022