Skip to main content

AgendaQuick™

View Agenda Item

Consent-Community Services   # 7.
Board of Supervisors
Integrated Waste Management
Meeting Date:
03/21/2023
Brief Title
Accept the construction of Waste Management Unit G Leachate Pond Improvements as complete
From:
Leslie Lindbo, Interim Director, Department of Community Services
Staff Contact:
Jeff Kieffer, Principal Civil Engineer, Department of Community Services, x8855
Supervisorial District Impact:
District 3

Subject

Accept as complete the Waste Management Unit G Leachate Pond Improvements at the landfill, constructed by RJ Gordon Construction, Inc. (No general fund impact) (Lindbo/Kieffer)

Recommended Action

  1. Accept as complete the Waste Management Unit G Leachate Pond Improvements at the landfill, constructed by RJ Gordon Construction, Inc.; 
     
  2. Adopt a finding that competitive bidding for the work described in Contract Change Orders No. 9 and 10 for the Waste Management Unit G Leachate Pond Improvements project would have been unavailing, impractical, and would not have produced any public advantage; 
     
  3. Approve Change Order Nos. 9 and 10 with RJ Gordon and authorize the Interim Director of the Division of Integrated Waste Management (DIWM) to sign; and 
     
  4. Authorize the Interim Director of the Division of Integrated Waste Management to sign and record the Notice of Completion for the Waste Management Unit G Leachate Pond Improvements.

Strategic Plan Goal(s)

Sustainable Environment

Reason for Recommended Action/Background

Waste Management Unit G (WMU G) was originally constructed in 1996 as the landfill’s first lined leachate and liquid waste pond and is the primary receiving pond for the landfill’s liquid and septic waste customers.  As originally constructed, the exterior levees of WMU G were not high enough to protect the pond from the recently updated 100-year flood elevation.  Additionally, the WMU G containment structures were nearing the end of their useful life and needed replacement. 

The Board of Supervisors (BOS) approved the plans and specifications, authorized the Director of the Division of Integrated Waste Management (Director) to make any design changes mandated by the California Regional Water Quality Control Board – Central Valley Region (Water Board) and authorized the division to advertise for competitive bids on May 21, 2019.  Due to delays receiving comments from the Water Board, project financing and staffing availability, the project was not advertised for bids until April 2022.  Three bids were received on June 9, 2022, with RJ Gordon Construction submitting the lowest responsive and responsible bid. Accepting and recording the Notice of Completion will allow final project close-out.

Construction began in August 2022 with a short construction schedule to minimize impacts to landfill operations and the many liquid waste customers the landfill serves.  An early completion bonus of $10,000 per day was also included in the specification to incentivize the contractor to complete the construction ahead of schedule.  RJ Gordon Construction did complete the project ahead of Schedule by 17 days, earning a bonus of $170,000.  This is included as Change Order 10.  The cost savings for the landfill and the ability to increase the amount of liquid waste received following this early completion offsets this bonus.  At the May 19, 2019, Board of Supervisors meeting the DIWM Director was authorized to approve all change orders up to the maximum allowable under state law.  In the case of this project, the maximum allowable is $260,301.56.  Several unanticipated issues arose during construction activities which resulted in the Director approving change orders totaling $239,414.25, thus nearing this limit.  Approval of Change Orders 9 and 10 will bring the total change order amount for the project to $491,710.03.  Change Order 9 represents work associated with field modifications to the grading, piping, and sump access point necessary for a complete and functional pond.  Change Order 10 is for the early completion bonus. 

In accordance with the project specifications, following approval of the Notice of Completion, County staff will issue a proposed final pay estimate to the contractor. The contractor will then have 30 days to approve said pay estimate or provide a written statement of all claims.  Staff does not anticipate any claims or issues with the proposed final pay estimate and project close-out. The final construction cost for the project, including approved change orders, is $5,326,329.49.

Collaborations (including Board advisory groups and external partner agencies)

County Counsel was consulted on the early completion bonus calculation.

Approval of the construction is also required by the Water Board, which was received on January 9, 2023.

Competitive Bid Process/Vendor Performance

Bids Received
 
Bidder Bid
RJ Gordon Construction $4,956,031.28
Sukut Construction $5,447,424.00
Teichert Construction $6,214,543.00

Fiscal Impact

Fiscal impact (see budgetary detail below)

Fiscal Impact (Expenditure)

Total cost of recommended action:
$    252,296
Amount budgeted for expenditure:
$    252,296
Additional expenditure authority needed:
$   
One-time commitment:
Yes

Source of Funds for this Expenditure

Sanitation Enterprise
$252,296

Further explanation as needed:

The additional cost of recommended action is for Change Orders 9 and 10. Sufficient funds are available in the capital improvement portion of the DIWM budget for these changes. (No general fund impact)

Attachments

Form Review

Inbox Reviewed By Date
Marissa Juhler Marissa Juhler 03/08/2023 12:56 PM
Financial Services KauXue Thao 03/09/2023 11:18 AM
County Counsel Hope Welton 03/09/2023 12:04 PM
Form Started By:
Jeff Kieffer
Started On:
12/21/2022 10:43 AM
Final Approval Date:
03/10/2023