Brief Title
Reimbursement of Contingency Funds Q1
From:
Leslie Lindbo, Interim Director, Department of Community Services
Staff Contact:
Todd N. Riddiough, Interim Director of Public Works, Department of Community Services, x8039
Supervisorial District Impact:
Countywide

Subject

Approve reimbursement of $108,298 to the Road Fund for FY 22/23 Quarter 1 activities for efforts to assemble construction ready documents, to pursue grant application opportunities, and implement construction of road projects and adopt a budget resolution increasing appropriations and estimated revenues for the Road Fund by $108,298. (General fund impact $108,298) (4/5 vote required) (Lindbo/Riddiough)

Recommended Action

  1. Approve reimbursement of $108,298 to the Road Fund for FY 22/23 Quarter 1 activities for efforts to assemble construction ready documents, to pursue grant application opportunities, and implement construction of road projects; and
     
  2. Adopt a budget resolution increasing appropriations and estimated revenues for the Road Fund by $108,298 for reimbursement of project activities for FY 22/23 Quarter 1.

Strategic Plan Goal(s)

Safe Communities

Reason for Recommended Action/Background

In the Fiscal Year (FY) 22-23 Adopted Budget, the Board of Supervisors allocated $550,000 in contingency funds to the Department of Community Services for efforts to assemble construction ready documents, to pursue grant application opportunities, and implement construction of road projects.
 
For Quarter 1 of FY 22-23, County staff efforts of $108,298 were expended toward work on the following projects that are in process:
  • Ongoing efforts by our grant writing consultant to pursue funding opportunities for the County Road 32A Railroad Crossing Relocation Project
  • Ongoing design efforts by our road design consultant for the planned County Road 31 Bike Lane and Road Rehabilitation Project
  • Ongoing design and right-of-way acquisition efforts for the County Road 41 Washout Realignment Project
  • Began design efforts on the 2023 Pavement Preservation Project

The attached budget resolution is needed to complete the $108,298 reimbursement to the Road Fund using the contingency funds. Such appropriations are authorized with a four-fifths vote of the Board of Supervisors pursuant to Government Code section 29125.

With approval of this reimbursement, $441,702 will remain in this contingency funding for the remainder of FY 22-23.

Collaborations (including Board advisory groups and external partner agencies)

County Administrator’s Office
County Counsel

Competitive Bid Process/Vendor Performance

N/A

Fiscal Impact

Fiscal impact (see budgetary detail below)

Fiscal Impact (Expenditure)

Total cost of recommended action:
$    108,298
Amount budgeted for expenditure:
$    0
Additional expenditure authority needed:
$    108,298
One-time commitment:
Yes

Source of Funds for this Expenditure

General Fund–Roads Cont.
$108,298

Further explanation as needed:

Shown in Adopted Budget FY22-23 Total Appropriation for Contingencies for “Roads” at $550,000. This is the first reimbursement request for FY22-23 efforts.

Attachments

Form Review

Inbox Reviewed By Date
Todd Riddiough (Originator) Todd Riddiough 01/09/2023 09:50 AM
Financial Services crinde 01/17/2023 09:11 AM
County Counsel Hope Welton 01/17/2023 09:36 AM
Form Started By:
Todd Riddiough
Started On:
07/13/2022 10:09 AM
Final Approval Date:
01/18/2023