Skip to main content

AgendaQuick™

View Agenda Item

Consent-Community Services   # 8.
Board of Supervisors
Public Works
Meeting Date:
03/11/2025
Brief Title
Right of Way Purchase Agreements
From:
Leslie Lindbo, Director, Department of Community Services
Staff Contact:
Lilia Razo, Principal Civil Engineer, Department of Community Services, x8845
Supervisorial District Impact:
District 2

Subject

Approve agreement with Oeste Ranch Partners, LLC in the amount of $212,440 for the acquisition of a roadway and utility easement, as well as a temporary construction easement for the County Road 98 Bike and Safety Improvement Project, Phase II. (No general fund impact) (Lindbo/Razo)

Recommended Action

  1. Approve agreement with Oeste Ranch Partners, LLC in the amount of $212,440 for a roadway and utility easement, as well as a temporary construction easement for the County Road 98 Bike and Safety Improvement Project, Phase II (Attachment A); and
     
  2. Authorize the Director of Public Works to execute the easement purchase agreements, approve payment, open escrow, accept the easements, extend the temporary construction easement (if necessary), and record the grant deeds once the signed grant deeds have been received and escrow has closed.

Strategic Plan Goal(s)

Thriving Residents

Reason for Recommended Action/Background

A permanent roadway and utility easement and a temporary construction easement are required on this property for the County Road (CR) 98 Safety Improvement Project, Phase II. Monument, ROW Inc., the County’s property acquisition consultant, had the easement interests to be acquired, appraised and worked with the property owner to come to a mutually acceptable purchase agreement (Attachment A).

Background

The CR 98 Bike and Safety Improvement Project, Phase II (Project) will extend the improvements completed in 2014 between Woodland and County Road 29 southward to the Solano County line. The Project has received federal transportation funding for the preliminary engineering and project development, right of way, and construction phases through the Sacramento Area Council of Governments (SACOG) in the amounts of $2,364,782, $4,180,00, and $8,725,000, respectively.

On December 11, 2018, the Board of Supervisors approved staff’s recommendation for roundabouts for the intersection treatment for the main intersections with CR 98. Staff moved forward with the environmental phase of the Project. The Natural Environment Study (NES) was approved by Caltrans on January 27, 2021, and the Board of Supervisors adopted the Initial Study/Mitigated Negative Declaration (IS/MND) on April 26, 2022, as the appropriate level of environmental review in accordance with the California Environmental Quality Act (CEQA). On November 7, 2022, Caltrans concluded that a Categorical Exclusion was the appropriate determination for the project under the National Environmental Policy Act (NEPA).

Caltrans authorized the County to initiate the right-of-way (ROW) phase on December 7, 2022. Subsequently, the ROW consultant, Monument ROW, Inc. (Monument) and the survey consultant, Mark Thomas & Company, Inc. (Surveyor), began their work. The Surveyor placed stakes along all properties impacted by the Project. The stakes were used by Pattison & Associates, a subconsultant to Monument, to perform appraisals and develop appraisal reports for all acquisition areas to determine fair market value. In mid-September 2023, Monument began to contact all property owners to present written offers to acquire the easements needed for the Project.  Due to harvest season, most property owners elected to receive their offer packages via mail. We expect the right of way acquisition process to continue through 2025.

On November 7, 2023, staff provided a project update and recommended to the Board to authorize staff to phase the Project's construction due to unsuccessful attempts to obtain additional grants to fund the entire cost of construction. Based on the recommendation, the first construction phase would be between Solano County and Hutchison Drive.

The ROW phase is fully funded, and staff is focusing first to acquire the ROW needed for the utility relocation and the area within the first construction phase.  All utilities will be relocated to the east side of CR 98. Utility providers are working on the design for the entire project and have tentatively scheduled to relocate all facilities in fall of 2026.

Staff is also working with willing property owners as they review and respond to their offer packages delivered in mid-September 2023, which is the case with the attached agreement.

Collaborations (including Board advisory groups and external partner agencies)

County Counsel has approved the agreement as to form.

Competitive Bid Process/Vendor Performance

N/A

Fiscal Impact

Fiscal impact (see budgetary detail below)

Fiscal Impact (Expenditure)

Total cost of recommended action:
$    212,440
Amount budgeted for expenditure:
$    212,440
Additional expenditure authority needed:
$    0
One-time commitment:
Yes

Source of Funds for this Expenditure

Road Fund
$212,440

Further explanation as needed:

The cost of the purchase will be reimbursed with federal funds at a rate of 88.53% of the cost, or $188,073.13. The remaining $24,366.87 will be paid from Highway User Tax Account funds. Sufficient funds were budgeted in the fiscal year 2024/25 Road Fund budget for the Project to cover this purchase.

Attachments

Form Review

Inbox Reviewed By Date
Todd Riddiough (Originator) Todd Riddiough 02/15/2025 10:58 AM
Todd Riddiough (Originator) Todd Riddiough 02/28/2025 01:34 PM
Kimberly Hood Kimberly Hood 02/28/2025 03:55 PM
Financial Services mrobertson 03/03/2025 09:06 AM
County Counsel Hope Welton 03/03/2025 09:09 AM
Berenice Espitia Berenice Espitia 03/03/2025 01:46 PM
Form Started By:
Todd Riddiough
Started On:
12/28/2024 11:16 AM
Final Approval Date:
03/03/2025