Skip to main content

AgendaQuick™

View Agenda Item

Consent-Community Services   # 8.
Board of Supervisors
Public Works
Meeting Date:
02/21/2023
Brief Title
Reimbursement of Contingency Funds Q2
From:
Leslie Lindbo, Interim Director, Department of Community Services
Staff Contact:
Todd N. Riddiough, Principal Civil Engineer, Department of Community Services, x8039
Supervisorial District Impact:
Countywide

Subject

Approve reimbursement of $233,862 to the Road Fund for 2022-23 Quarter 2 activities for efforts to assemble construction ready documents, to pursue grant application opportunities, and implement construction of road projects and adopt budget resolution increasing appropriations and estimated revenues for the Road Fund by $233,862. (General fund impact $233,862) (4/5 vote required) (Lindbo/Riddiough)

Recommended Action

  1. Approve reimbursement of $233,862 to the Road Fund for FY2022-23 Quarter 2 activities for efforts to assemble construction ready documents, to pursue grant application opportunities, and implement construction of road projects; and
     
  2. Adopt budget resolution increasing appropriations and estimated revenues for the Road Fund by $233,862 for reimbursement of project activities for FY2022-23 Quarter 2.

Strategic Plan Goal(s)

Safe Communities

Reason for Recommended Action/Background

In the Fiscal Year (FY) 22-23 Adopted Budget, the Board of Supervisors allocated $550,000 in contingency funds to the Department of Community Services for efforts to assemble construction ready documents, to pursue grant application opportunities, and implement construction of road projects.

For Quarter 2 of FY 22-23, County staff efforts of $233,862 were expended toward work on the following projects that are in process:
  • Ongoing efforts by our grant writing consultant to pursue funding opportunities for the County Road 32A Railroad Crossing Relocation Project
  • Ongoing design efforts by our road design consultant for the planned County Road 31 Bike and Safety Improvement Project
  • Ongoing design and right-of-way acquisition efforts for the County Road 41 Washout Realignment Project
  • Continuing design efforts on the 2023 Pavement Preservation Project
  • Began design efforts on the 2023 Road Rehabilitation Project
  • Began design efforts on the Russell Boulevard Bike and Safety Improvement Project
The attached budget resolution is needed to complete the $233,862 reimbursement to the Road Fund using the contingency funds. Such appropriations are authorized with a four-fifths vote of the Board of Supervisors pursuant to Government Code section 29125.

With approval of this reimbursement, $207,840 will remain in this contingency funding for the remainder of FY 22-23.

Collaborations (including Board advisory groups and external partner agencies)

County Administrator’s Office
County Counsel

Competitive Bid Process/Vendor Performance

N/A

Fiscal Impact

Fiscal impact (see budgetary detail below)

Fiscal Impact (Expenditure)

Total cost of recommended action:
$    233,862
Amount budgeted for expenditure:
$    0
Additional expenditure authority needed:
$    233,862
One-time commitment:
Yes

Source of Funds for this Expenditure

General Fund–Roads Cont.
$233,862

Further explanation as needed:

The FY22-23 Adopted Budget total appropriations for Contingencies set aside for "Roads" was $550,000. This is the second reimbursement request for FY22-23 efforts.

Attachments

Form Review

Inbox Reviewed By Date
Kimberly Hood Kimberly Hood 02/07/2023 02:18 PM
Kimberly Hood Kimberly Hood 02/07/2023 02:18 PM
Financial Services KauXue Thao 02/13/2023 04:44 PM
County Counsel Hope Welton 02/13/2023 05:08 PM
Form Started By:
Todd Riddiough
Started On:
01/24/2023 09:49 AM
Final Approval Date:
02/15/2023