Consent-Community Services # 7.
Board of Supervisors
County Service Areas
- Meeting Date:
- 06/06/2023
- Brief Title
- LSCE Arsenic Contract Amendment
From:
Leslie Lindbo, Director, Department of Community Services
Staff Contact:
Kimberly Villa, Community Services Analyst, Department of Community Services, x8431
Supervisorial District Impact:
District 3
Subject
Approve third amendment to Agreement No. 19-253 with Luhdorff & Scalmanini Consulting Engineers, Inc. for the engineering and design of the arsenic treatment facility at Wild Wings County Service Area to extend the term for one additional year through June 30, 2024. (No general fund impact) (Lindbo/Villa)
Recommended Action
Approve third amendment to Agreement No. 19-253 with Luhdorff & Scalmanini Consulting Engineers, Inc. for the engineering and design of the arsenic treatment facility at Wild Wings County Service Area to extend the term for one additional year through June 30, 2024.
Strategic Plan Goal(s)
![]() |
Safe Communities |
Reason for Recommended Action/Background
The Canvasback well in the Wild Wings County Service Area (CSA) is currently on "Emergency Standby" status due to exceeding the State arsenic standards. In October 2019, the CSA issued a request for proposals (RFP) for an arsenic treatment project to reduce arsenic levels in both Wild Wings wells (Canvasback and Pintail wells). On December 17, 2019, the County entered into an agreement with Luhdorff & Scalmanini, Consulting Engineers (LSCE) to oversee the arsenic treatment system project for the Wild Wings CSA wells (Attachment A). This project was anticipated to be completed in December 2021. LSCE completed analysis on water demands and conceptual treatment options. An amendment was entered to conduct pilot testing of the conceptual treatment options for additional information on the options available. In June 2021, the Canvasback well had to be taken completely offline due to diminished water levels. The project was put on hold as a result of the diminished water levels. In May 2022, the Board of Supervisors approved an amendment to extend the term of the LSCE agreement an additional year through June 30, 2023. Since this last extension, the plans and specification of construction have been drafted, and staff plans to take the design out to bid in 2023. Additional engineering is required to ensure the construction bidder builds the arsenic facility according to plan.
The current contract term is set to expire on June 30, 2023. The proposed third amendment to Agreement No. 19-253 (Attachment B) will extend the term of the Agreement with LSCE for one additional year, through June 30, 2024 to allow sufficient time to oversee project construction.
The current contract term is set to expire on June 30, 2023. The proposed third amendment to Agreement No. 19-253 (Attachment B) will extend the term of the Agreement with LSCE for one additional year, through June 30, 2024 to allow sufficient time to oversee project construction.
Collaborations (including Board advisory groups and external partner agencies)
County Counsel, Wild Wings County Service Area Advisory Committee
Competitive Bid Process/Vendor Performance
A competitive bid process was completed in 2019. Luhdorff & Scalmanini, Consulting Engineers was the selected bidder.
Vendor Performance
The Department confirms Luhdorff & Scalmanini has performed satisfactorily on the current agreement.
Vendor Performance
The Department confirms Luhdorff & Scalmanini has performed satisfactorily on the current agreement.
Fiscal Impact
No Fiscal Impact
Fiscal Impact (Expenditure)
- Total cost of recommended action:
- $ 0
- Amount budgeted for expenditure:
- $
- Additional expenditure authority needed:
- $
- One-time commitment:
- Yes
Source of Funds for this Expenditure
- General Fund
- $0
Further explanation as needed:
This Amendment extends the term of the Agreement
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Financial Services | KauXue Thao | 05/16/2023 08:09 AM |
| County Counsel | Hope Welton | 05/16/2023 09:36 AM |
| Kimberly Hood | Kimberly Hood | 05/16/2023 03:08 PM |
- Form Started By:
- kvilla
- Started On:
- 05/10/2023 11:48 AM
- Final Approval Date:
- 05/16/2023