Approval of the lowest and best bid in the amount of $450,000.00, from Cook Consulting, LLC, for the Haskell Pump Station, Project No. 2022021, as recommended by Cowan Group Engineering, or take other necessary action. (Mike Stewart)
BACKGROUND:
The Haskell Booster Station is in need of repair due to pipe leaks, failing pumps and other equipment. City staff requested design plans and bids for the project to replace the pumps, piping, valves, electrical, driveway, and metal roofing. These proposed improvements will alleviate leaks and protect the structure, its contents, and employees. It will also improve safety at the site as well as operations overall. Bids were solicited in the newspaper and online in multiple bid rooms. Three (3) competitive bids were received and were within the expected budgeted amount for the project.
Cowan Group Engineering is recommending an award to the low bidder, Cook Consulting, LLC.
The project is being funded through the American Recovery and Reinvestment Act being administered by the Oklahoma Water Resources Board.
RECOMMENDED ACTION:
Approve lowest and best bid to Cook Consulting, LLC, for the Haskell Pump Station in the amount of $450,000.00
Fiscal Impact
FUNDING SOURCE:
ARPA Funds