ITEM 23
City Council Memorandum Public Works & Utilities Memo No. CP22-052
Date:
January 24, 2022
To:
Mayor and Council
Thru:
Joshua H. Wright, City Manager
Andy Bass, Deputy City Manager
John Knudson, Public Works and Utilities Director
Andrew Goh, Capital Projects Manager
From:
Kimberly Moon, Principal Engineer
Subject:
Construction Contract No. ST2006.401, with B&F Contracting, Inc., for Traffic Signal Installation at Warner Road and Nevada Street
Proposed Motion:
Move City Council award Construction Contract No. ST2006.401, to B&F Contracting, Inc., for Traffic Signal Installation at Warner Road and Nevada Street, in an amount not to exceed $594,681.82.
Background/Discussion:
In response to a resident request, a signal warrant evaluation was conducted at the Warner Road and Nevada Street intersection. Results of the study showed the traffic movements, volumes, and conditions warrant additional traffic control devices to enhance safety and traffic flow. Staff proposes the installation of a traffic signal at the intersection of Warner Road and Nevada Street.
The project scope of work includes the installation of traffic control equipment, wireless vehicle detection, preemption equipment, and a closed-circuit television camera. The project also includes pedestrian curb ramps on each of the intersection corners to comply with the American with Disabilities Act guidelines, and removal of the roadway light in the median on the east leg of the intersection. The contract completion time is 210 calendar days following Notice to Proceed.
Evaluation:
Two (2) bids were opened on October 28, 2021. The bid results were as follows:
Contractor
Bid Total
B&F Contracting, Inc.
$594,681.82
Combs Construction Company, Inc.
$674,267.05
Fiscal Impact
Account No.
Fund Name
Program Name
Dollar Amount
CIP Funded Y/N
411.1560.6517.6DS322
Streets General Obligation Bonds
Traffic Signal Additions
$594,681.82
Y
Attachments
Location Map
Contract - B&F Contracting