ITEM 15
City Council Memorandum Development Services Memo No. CP25-030
Date:
October 14, 2024
To:
Mayor and Council
Thru:
Joshua H. Wright, City Manager
Andy Bass, Deputy City Manager
Kevin Snyder, Development Services Director
Daniel Haskins, Capital Projects Division Manager
From:
Alyssa Siqueiros, Construction/Design Project Manager
Subject:
Professional Services Agreement No. DS2402.201, with Greenlight Traffic Engineering, for the Traffic Signal at Gilbert Road and Amanda Boulevard
Design
Services
Proposed Motion:
Move City Council award Professional Services Agreement No. DS2402.201 to Greenlight Traffic Engineering, for the Traffic Signal at Gilbert Road and Amanda Boulevard
Design
Services, in an amount not to exceed $115,622.46.
Background/Discussion:
The purpose of the project is to design a signalized intersection at South Gilbert Road and East Amanda Boulevard. The city received requests from nearby residents, as well as the City of Chandler Fire Department, to install a traffic signal at this intersection. The city completed a traffic signal study in
2021,
which determined a traffic signal is warranted at this location.
The project scope of work will consist of the design of a signalized intersection, as well as the evaluation of the existing conditions relating to ADA compliance, pavement and sidewalk quality, and streetlighting. In addition to the traffic signal system design, the project design will also incorporate pavement marking and signing, Intelligent Transportation Systems (ITS) components, fire department vehicle pre-emption, and various civil improvements.
The agreement completion time is 450 calendar days following Notice to Proceed.
Evaluation:
The selection process was conducted in accordance with city policy and procedure and state law. This project is being performed under the On-Call Consultant Pre-Qualified List for Transportation Services. Staff recommends approval of this agreement with Greenlight Traffic Engineering based on qualifications, relevant firm experience, team experience, project understanding, and project approach.
Financial Implications:
This project will be locally funded through the Traffic Signal Additions program in the amount of $115,622.46.
Fiscal Impact
Account No.
Fund Name
Program Name
Dollar Amount
CIP Funded Y/N
411.1560.6516.6DS322
Streets General Obligation Bonds
Traffic Signal Additions
$115,622.46
Y
Attachments
Location Map
DS2402.201 Agreement