ITEM 22
City Council Memorandum Public Works & Utilities Memo No. CP23-056
Date:
November 10, 2022
To:
Mayor and Council
Thru:
Joshua H. Wright, City Manager
Andy Bass, Deputy City Manager
John Knudson, Public Works and Utilities Director
Kimberly Moon, Capital Project Manager
From:
Sandra Story, Engineering Project Manager
Subject:
Construction Manager at Risk Agreement No. WW2206.251, with PCL Construction, Inc., for the Reclaimed Water Conveyance Improvements Pre-Construction Services
Proposed Motion:
Move City Council award Construction Manager at Risk Agreement No. WW2206.251, to PCL Construction, Inc., for the Reclaimed Water Conveyance Improvements Pre-Construction Services, in an amount not to exceed $628,545.94.
Background/Discussion:
In October 2021, the City executed a reclaimed water agreement with Intel Corporation for additional reclaimed water supply. As part of this agreement, it is necessary for the City to convey additional volumes of reclaimed water from the Airport Water Reclamation Facility (AWRF), located at 905 E. Queen Creek Road, to the Ocotillo Water Reclamation Facility (OWRF) for delivery to Intel's campus. New infrastructure necessary for this conveyance includes additional reclaimed water pipe on both the AWRF and OWRF sites, new pipeline within the City’s rights of way, additional pumping systems at the AWRF site, and the addition of up to four aquifer storage and recovery wells at the Tumbleweed Park Recharge Facility.
The project scope of work includes constructability studies and review, value engineering, project planning and scheduling, assistance in the coordination of contract documents, and preparation of Guaranteed Maximum Price packages. The Agreement completion time is 720 calendar days following Notice to Proceed.
Evaluation:
The selection process was followed in accordance with City policy and procedure and State law. Staff recommends agreement award to PCL Construction, Inc., based on qualifications, relevant firm experience, team experience, project understanding, and project approach.
Financial Implications:
The total project will be funded 20% by the City of Chandler, with the remaining 80% reimbursed by Intel (20%) and the State of Arizona Title 42 funding for public infrastructure per the City’s October 2021 Reclaimed Water Agreement with Intel Corporation (80%).
Fiscal Impact
Account No.
Fund Name
Program Name
Dollar Amount
CIP Funded Y/N
615.3910.6817.6WW690
Wastewater Operating
Reclaimed Water Conveyance Phase II
$628,545.94
Y
Attachments
Location Map
Agreement - PCL Construction