ITEM 25
City Council Memorandum Public Works & Utilities Memo No. CP22-170
Date:
May 23, 2022
To:
Mayor and Council
Thru:
Joshua H. Wright, City Manager
Andy Bass, Deputy City Manager
John Knudson, Public Works and Utilities Director
Kimberly Moon, Acting Capital Projects Manager
From:
Daniel Haskins, Engineer
Subject:
Professional Services Agreement No. ST1616.451, with Consultant Engineering, Inc., for the Ocotillo Road Improvements - Gilbert Road to 148th Street
Construction Management
Services
Proposed Motion:
Move City Council award Professional Services Agreement No. ST1616.451, to Consultant Engineering, Inc., for the Ocotillo Road Improvements - Gilbert Road to 148th Street
Construction Management
Services, in an amount not to exceed $678,806.
Background/Discussion:
The project will complete improvements on Ocotillo Road for two through lanes in the eastbound and westbound directions from Gilbert Road to 148th Street, per the 2010 Transportation Master Plan, and subsequent 2019 Transportation Master Plan Update. The project scope of work consists of pre-construction assistance, utility coordination, construction management, contract oversight, construction administration, construction inspection, materials testing quality assurance, Federal Highway Administration funding compliance, construction contract close-out, and Public Outreach services. The contract completion time is 360 calendar days following Notice to Proceed. Construction is anticipated to commence in late summer or early fall 2022.
A related Professional Services Agreement with Ardurra Group, Inc., for the Ocotillo Road Improvements - Gilbert Road to 148th Street Post Design Services, is also scheduled for this City Council meeting.
A related Construction Contract with Haydon Building Corp., for the Ocotillo Road Improvements - Gilbert Road to 148th Street, is also scheduled for this City Council meeting.
Evaluation:
The selection process was conducted in accordance with City policy and procedure and State law. Staff recommends approval of this agreement with Consultant Engineering, Inc., based on qualifications, relevant firm experience, team experience, project understanding, and project approach.
Fiscal Impact
Account No.
Fund Name
Program Name
Dollar Amount
CIP Funded Y/N
415.3310.6517.6ST641
Arterial Street Impact Fees
Ocotillo Rd-Gilbert Rd to 148th St
$678,806
Y
Attachments
Location Map
Agreement - Consultant Engineering, Inc.