CITY OF CORTEZ
123 ROGER SMITH AVENUE
CORTEZ, CO 81321
October 25, 2022
Agenda Item: 7.b.
MEMO TO:
Honorable Mayor and City Council
FROM:
Brian Peckins, Director of Public Works
SUBJECT:
Bid Results on
Rehabilitation of the City’s 2-MG Drinking Water Storage Tank #3
BACKGROUND
The City’s water storage tanks are cleaned and inspected on a regular schedule. During the last inspection in 2019, it was noted that it was time to have the water tanks repaired and recoated. The repairs are necessary because of rusty interior parts, which are mostly above the water level. This is due to the chlorine gas oxidizing the metal above the water. Tanks #1 and #2 were rehabilitated last year, and work on Tank #3 is scheduled to begin in 2022, with a completion date of March 10, 2023. Tank #3 has been in service since 1962.
This project consists of the rehabilitation of the City’s 2-MG above-ground welded steel drinking water storage Tank #3. This work will include spot steel shell and structural support repairs and replacements; clip replacements; floor plate spot replacements; media blasting; epoxy coating the interior and exterior; and other appurtenant work on tank #3. The tank is approximately 48 feet high and 84 feet in diameter.
ISSUES
The City’s contract engineer, SGM out of Durango, prepared the bid plans and specifications for this project. A pre-bid meeting was conducted on September 21, 2022, with all interested prospective bidders. Bids were opened on October 12, 2022, with five bids received, as shown below. All bidders submitted the mandatory 5% bid bond with their bid.
Classic Protective Coatings, Inc. - Menomonie, WI $1,129,300
Riley Industrial Services, Inc. – Farmington, NM $ 959,591
TMI Coatings, Inc. – St. Paul, MN $1,015,000
Viking Painting LLC – Omaha, NE $1,433,850
WBS Coatings, Inc. – Grand Junction, CO $ 715,646
Engineer’s Estimate $ 943,855
Capital Projects Budget $ 750,000
RECOMMENDATION
Staff recommends awarding the bid to WBS Coatings, Inc. as low bidder at $715,646. WBS is very capable of handling this project and is able to meet our schedule. The monies have been budgeted in the Water Capital Fund.
Attachments
Bid Tab - Tank #3 Rehabilitation