GARLAND
PURCHASING REPORT
Agenda Item 2.j.
City Council Regular Session Agenda
Meeting Date:
07/11/2023
Item Title:
Lonnecker Drive Wastewater Main Replacement
Submitted By:
Michael Brinkmann
Bid Number:
0787-23
Purchase Justification:
The request is to provide construction services to replace approximately 2,600 linear feet of 18-inch, 12-inch, and 8-inch wastewater main by open cut including manholes and service laterals. The project also includes approximately 2,500 square yards of concrete paving for street, driveway, and curb as well as gutter replacements and 500 square yards of sodding. The wastewater mains are located within the right-of-way of Lonnecker Drive between West Miller Road and Wood Drive. An optional contingency is included for any additional work that may be required.
Evaluation:
A request for bids was issued per Purchasing procedures. Three (3) bids were received and evaluated with Flow-Line Construction, Inc. submitting the Straight Low Bid.
Award Recommendation:
Vendor
Item
Amount
Flow-Line Construction, Inc.
All
$1,598,226.00
Optional Contingency
180,000.00
TOTAL:
---------------------------
$1,778,226.00
Basis for Award:
Straight Low Bid
Purchase Requisition #:
49291
Fiscal Impact
Total Project/Account:
$16,713,053
Expended/Encumbered to Date:
$8,210,424
Balance:
$8,502,629
This Item:
$1,778,226
Proposed Balance:
$6,724,403
Account #:
230-4149-3212400-9305, 235-4149-3212400-9305
Fund/Dept/Project – Description and Comments:
Wastewater CIP / Infiltration Correction Program
Attachments
Bid Recap
Fiscal Reference:
Budget Type:
CIP
Fiscal Year:
2023
Document Location:
Page 245
Budget Director Approval:
Allyson Bell Steadman
Approval Date:
06/29/2023
Purchasing Director Approval:
Gary L. Holcomb
Approval Date:
06/26/2023