Print
Reading Mode
Return
ITEM #: 6.
DATE: 12/09/2024
AI #:2369
CITY COUNCIL ACTION REPORT
SUBJECT:
AUTHORIZATION OF THE EXPENDITURE OF CONSTRUCTION FUNDS FOR APPROVED CIP PROJECT #42088 – DILEMMA ZONE ADVANCE DETECTION AND ITS UPGRADES
STAFF PRESENTER(S):
Steve Scinto, Director of Engineering
OTHER PRESENTER(S):
Hugh Bigalk, City Traffic Engineer
SUMMARY
A request to authorize the expenditure of funds up to $1,650,000 for Capital Improvement Program (CIP) Project #42088 – Dilemma Zone Advance Detection and ITS Upgrades.
STRATEGIC PLAN ALIGNMENT
RECOMMENDATION
Authorize the expenditure of funds up to $1,650,000 for Capital Improvement Program (CIP) Project #42088 – Dilemma Zone Advance Detection and ITS Upgrades. (Steve Scinto, Director of Engineering)
FISCAL IMPACT
CIP Project #42088 – Dilemma Zone Advance Detection and ITS Upgrades is currently programmed in the FY2025 CIP with a total project budget of $1,650,000 with an estimated completion date of June 2025.
BACKGROUND AND PREVIOUS ACTIONS
Per city of Goodyear Resolution 08-1255, all expenditures of budgeted funds in excess of $500,000 must obtain Council approval.
On June 10, 2024 (AI-1797), Council approved CIP #42088 - Dilemma Zone Advance Detection and ITS Upgrades in the adoption of Resolution No. 2024-2381 Determining and Adopting the Final Estimates of Proposed Revenues and Expenditures for the city of Goodyear for FY2025.
STAFF ANALYSIS
This Council Action Request is to obtain authorization for the expenditure of funds for materials and equipment of CIP Project #42088 – Dilemma Zone Advance Detection and ITS Upgrades. This request is to start the first year of a four-year capital improvement project intended to improve the efficiency of traffic signal operations and the safety at intersections in the City. The proposed improvements
include
hardware with expanded vehicle
detection
capable of covering dilemma zones and vehicle travel times. The dilemma zone is the area approaching a signalized intersection where drivers face a decision when the light turns yellow; whether to stop or proceed through the intersection
.
This
equipment will be purchased through a vendor and installation will be
performed
by city staff.