Resolution - Engineering:
Consider a resolution authorizing the Mayor to execute Amendment No. 1 to Contract 15754, with Parkhill, for providing final design and bid phase services for the Southeast Water Reclamation Plant, Plant 4 Secondary Clarifier Rehabilitation Project.
Item Summary
The Southeast Water Reclamation Plant (SEWRP) Plant 4 Secondary Clarifier Rehabilitation Project will provide for the replacement of the aging secondary clarifier infrastructure and equipment at the SEWRP.
On February 22, 2021, Parkhill, Inc. was awarded Contract 15754, for the preliminary design of the SEWRP Plant 4 Secondary Clarifier Rehabilitation project. Amendment No. 1 will authorize the Engineer to perform final design and bid phase services. It will increase the base contract by $49,500 and provide a contract extension of 365 days to complete the services.
Fiscal Impact
This contract in the amount of $49,500, is funded in Capital Improvements Project 92699, SEWRP Plant #4 Secondary Clarifier Rehabilitation.
Staff/Board Recommending
Jesica McEachern, Assistant City Manager
Attachments
Resolution
Amendment No.1
Original Contract
Location Map
Budget Detail
CIP Detail
AgendaQuick ©2005 - 2024 Destiny Software Inc.
All Rights Reserved.