Resolution - Public Works:
Consider a resolution authorizing the Mayor to execute Contract 16741, with Municipal Valve & Equipment, for the purchases of large distribution system valves for isolation of Pump Station 4.
Item Summary
The purpose of the Pump Station 4 Large Valve Project is to install new valves in order for the pump station to be shut down ahead of the Bailey County Line Improvements and Pump Station 4 Improvements Projects. The existing valves surrounding the pump station have outlived their useful design life and more recently have failed to shut down, when needed for repairs. This project is for purchase only of the valves.
In response to RFP 23-16741-TF, proposals were received and opened on February 17, 2022, from the following vendors.
Supplier
Location
Vector Controls
Plano, Texas
O Toole Industries
Lubbock, Texas
Municipal Valve & Equipment
Addison, Texas
Core and Main
Lubbock, Texas
SBIW, Inc.
San Ramon, California
The proposals were evaluated using the following criteria: 50 Points for Price, 30 Points for Meeting the Project Specifications, and 20 Points for Scheduled Total Time for Delivery. The maximum point value is 100 points. After the proposals were evaluated, the following rankings were given.
Supplier
Location
Points
Municipal Valve & Equipment
Addison, Texas
74.52
Vector Controls
Plano, Texas
72.05
SBIW, Inc.
San Ramon, California
62.00
Core and Main
Lubbock, Texas
45.50
O'Toole Industries
Lubbock, Texas
no specs submitted
The contract is awarded by the unit price. The total amount of the award is estimated based on expected quantities and actual expenditures may be more or less depending on actual quantities. The price per unit will not change.
The time for total delivery of all valves is 140 consecutive calendar days.
The pre-purchase of valves ahead of the construction contract will allow for better control of the project timelines, removing equipment delays from the project.
The Staff and Evaluation Committee recommend award of the unit price contract to the highest ranked proposal, Municipal Valve & Equipment, Inc. of Addison, Texas for $233,203.40.
Fiscal Impact
This contract for $233,203.40 is funded in CIP 92513, Pumping System Improvements Phase II
Staff/Board Recommending
Erik Rejino, Assistant City Manager
L. Wood Franklin, P.E., Division Director of Public Works
Attachments
Resolution - Municipal Valve and Equip.
PO - Municipal Valve and Equip.
Budget Detail
CIP Detail
Project Summary - Pump Station Valve Project
AgendaQuick ©2005 - 2024 Destiny Software Inc.
All Rights Reserved.