Resolution - Public Works Streets:
Consider a resolution authorizing the Mayor to execute Contract 17600, with Ti-Zak Concrete, Inc., for the 2023 Concrete Repair and Patching Project.
Item Summary
This project will provide for the repair of failed concrete curbs, ramps and valley gutters in the public road system in targeted areas. These targeted areas will then be ready for an overlay treatment the following year, the final step towards having the road system in superior condition.
In response to ITB 23-17006-KM, bids from the following vendors were received and opened on December 28, 2022.
Vendor
Amount
Lone Star Dirt and Paving, Lubbock, Texas
$2,427,500.00
Ti-Zack Concrete Inc., Le Center, Minnesota
$2,248,094.50
Blackstone Concrete Ventures, Lubbock, Texas
$2,250,000.00
Staff recommends award to the lowest bidder, Ti-Zack Concrete Inc. for the estimated amount of $2,248,094.50.
Time for completion is 120 consecutive calendar days with liquidated damages of $1,204.28 per day, for each consecutive calendar day after substantial completion set forth herein above for completion of this project.
This contract is awarded by unit price. The total amount of the award is estimated based on estimated quantities, actual expenditures may be more or less depending on actual needs the price per unit will not change, and expenditures will not exceed appropriated funds.
Fiscal Impact
This contract for $2,248,094.50 is funded in CIP 92794 - 2023 Street Maintenance.
Staff/Board Recommending
Erik Rejino, Assistant City Manager
L. Wood Franklin, P.E., Division Director of Public Works
Attachments
Resolution - Ti-Zack Concrete
Contract - Ti-Zack Concrete
Bid Form - Ti-Zack Contrete
Budget Detail
CIP Detail
Project Summary Sheet - Concrete Repair
AgendaQuick ©2005 - 2024 Destiny Software Inc.
All Rights Reserved.