Print
Reading Mode
Back to Calendar
Return
AI# 12961
Regular City Council Meeting
6.3.
11/05/2024:
Information
Agenda Item
Resolution - Engineering:
Consider a resolution authorizing the Mayor to execute Change Order No. 2 to Public Works Contract 16274, with ACME Electric Company, for the Southeast Water Reclamation Plant Effluent Pump Station No. 2 Improvements.
Item Summary
The purpose of the Southeast Water Reclamation Plant (SEWRP) Effluent Pump Station No. 2 Improvements Project is to upgrade mission-critical pumping and electrical components of the effluent pump station, to increase the efficiency and overall reliability of the Wastewater Treatment Plant operation.
Change Order No. 2 to Contract 16274 includes additional fiber lines, electrical conductor and fuse changes, high level strobe alarms, bypass pumping modifications, an insertion valve for piping isolation, and a bypass force main, for wastewater system reliability and functionality.
Staff recommends award of Change Order No. 2 to Contract 16274, with ACME Electric Company, for a cost of $703,902.96, with an additional 180 days for substantial completion.
Fiscal Impact
Change Order No. 2 in the amount of $703,902.96, is funded in Capital Improvements Project 92656, SEWRP Effluent Pump Station No. 2 Improvements.
Staff/Board Recommending
Erik Rejino, Assistant City Manager
Bailey Ratcliffe, P.E., Interim Director of Engineering/City Engineer
Attachments
Resolution
Change Order 2
Change Order 1
Original Contract
Location Exhibit
CIP Budget Detail
CIP Detail
AgendaQuick ©2005 - 2025 Destiny Software Inc.
All Rights Reserved.