Regular City Council Meeting
7.7.
12/07/2021:
Information
Agenda Item
Resolution - Engineering:
Consider a resolution authorizing the Mayor to execute Change Order No. 1 to Contract 15792, with MH Civil Constructors, Inc., for the construction of Pressure Zone Delineation and Elevated Storage Tank Off-Site Water Lines.
Item Summary
On April 5, 2021, the City Council awarded Contract 15792 to MH Civil Constructors, Inc. in the amount of $2,426,000, for the construction of the Pressure Zone Delineation and Elevated Storage Tank Off-Site Water Lines Project. The purpose of this project is to establish and delineate the pressure plane in the water distribution system between the east and west pressure zones, replace or rehabilitate broken valves along the pressure plane boundary, and install pipe where a proper pressure zone cannot be established within the current water system.
Change Order No. 1 will incorporate the installation of a 12-inch water line and associated pavement repairs, new 16-inch valves at 50th Street and Indiana Avenue, additional curb and gutter, traffic control, pavement repair, and a 24-inch line stop. Staff negotiated Change Order No. 1 with MH Civil Constructors, Inc. in the amount of $532,164, with 0 days of additional time.
Fiscal Impact
This change order in the amount of $532,164, is funded in Capital Improvements Project 92454, Water Lines Ahead of Street Paving.
Staff/Board Recommending
Jesica McEachern, Assistant City Manager
Attachments
Resolution
Change Order No.1
Location Exhibit
Budget Detail
CIP Detail
AgendaQuick ©2005 - 2024 Destiny Software Inc.
All Rights Reserved.