Resolution - Engineering:
Consider a resolution authorizing the Mayor to execute Change Order No. 1 to Contract 15872, with Horseshoe Construction, Inc., for providing construction services for the Low Pressure Supply Line Rehabilitation Project along Quaker Avenue.
Item Summary
On September 14, 2021, Horseshoe Construction, Inc. was awarded Contract 15872, for the construction of the Low Pressure Supply Line Rehabilitation Project. A 24-inch gate valve is required to fully isolate the existing 24-inch low pressure concrete line. This project includes the rehabilitation, by means of slip lining, of approximately 3.5 miles of an existing 24-inch low-pressure dilapidated water line, with a new 20-inch distribution main along Quaker Avenue, from Marsha Sharp Freeway to Clovis Road. The purpose of the project is to increase the capacity and reliability of the existing concrete transmission line that connects Pump Station 16 and Low Head B, utilizing a trenchless construction method.
Change Order No. 1 will increase the contract cost by $84,313.77 and provide 28 additional calendar days to complete the services.
Fiscal Impact
Change Order No. 1 in the amount of $84,313.77, is funded in Capital Improvements Project 92659, Low Pressure Supply Lining.
Staff/Board Recommending
Jesica McEachern, Assistant City Manager
Attachments
Resolution (c) - Horseshoe Construction
Change Order No.1
Budget Detail
CIP Detail
Location Exhibit