Regular City Council Meeting
6.8.
12/14/2021:
Information
Agenda Item
Resolution - Engineering:
Consider a resolution authorizing the Mayor to execute Amendment No. 2 to Contract 13870, with Plummer Associates, Inc., for professional engineering construction phase services for the construction of a new 8-million gallon ground storage tank at the North Water Treatment Plant.
Item Summary
The City is in contract with DN Tanks for the construction of a new 8-million gallon (MG) ground storage tank (GST) at the North Water Treatment Plant. Amendment No. 2 to Contract 13870, with Plummer Associates, Inc., will provide professional engineering construction phase services for the 8-MG GST project.
The contract amendment scope of services includes on-site full time Resident Project Representative (RPR) services, to verify proper installation of critical project components, and to enforce provisions of the contract documents. In addition, the RPR will review the monthly pay applications, will conduct progress meetings, will be responsible for coordination of all construction activities, and will coordinate with the project Engineer of Record. This contract amendment will add 200 days to the existing contract, but will not add any additional funding to the existing contract.
Fiscal Impact
Amendment No. 2 will have no fiscal impact to Capital Improvement Project (CIP) 92353, South Lubbock Water Treatment Plant Expansion and CIP 92539, Water Treatment Plant Improvements Phase III.
Staff/Board Recommending
Jesica McEachern, Assistant City Manager
Attachments
Resolution
Amendment No.2
Amendment 1
Original Contract
Location Exhibit
CIP Spreadsheet
CIP Detail