Resolution - Engineering:
Consider a resolution authorizing the Mayor to execute Change Order No. 1 to Contract 15819, with DN Tanks, LLC, for the construction of the new North Water Treatment Plant 8-Million Gallon Ground Storage Tank.
Item Summary
The City Council authorized Construction Contract 15819, with DN Tanks, LLC of Grand Prairie, Texas, on July 13, 2021, with a contract price of $8,326,400.00 and 515 calendar days for construction time. The Notice to Proceed was issued on September 13, 2021.
The purpose of Change Order No. 1 is in response to discovering an abandoned sewer treatment plant under the ground surface while performing earthwork for the new 8-Million Gallon Ground Storage Tank. This unanticipated discovery resulted in additional labor, equipment, time, and material, han originally estimated in the project design and bid.
The net increase in contract price due to Change Order No. 1 is $390,976.41, with an additional 83 days added to the construction time. The new contract amount is $8,717,376.41, with a contract time of 598 days.
Fiscal Impact
Change Order No. 1 in the amount of a $390,976.41, is funded in Capital Improvement Project 92660, NWTP 8 MG Ground Storage Tank.
Staff/Board Recommending
Jesica McEachern, Assistant City Manager
Attachments
Resolution
Change Order No.1
Original Contract
Location Exhibit
Budget Detail
CIP Detail
AgendaQuick ©2005 - 2024 Destiny Software Inc.
All Rights Reserved.