AI# 11496
Regular City Council Meeting
6.19.
04/11/2023:
Information
Agenda Item
Resolution - Engineering:
Consider a resolution authorizing the Mayor to execute Change Order No. 2 to Contract 6114, with Lone Star Dirt & Paving Ltd., for 114th Street Paving Improvements from Slide Road to Quaker Avenue.
Item Summary
The purpose of this project is to improve 114th Street between Slide Road and Quaker Avenue, to a 5-lane minor arterial, in accordance with the City of Lubbock Thoroughfare Master Plan.
Executed Change Order No. 1 included additional bid tab items for conduit, pavement markers, ground boxes, surface preparation and pavement sealer, along with quantity adjustments for sidewalk included on the original bid tab.
Per RFP 22-16114-TF, Change Order No. 2 to Contract 16114 includes additional bid tab items for the relocation of existing water infrastructure. The water line is critical to the system and is currently in conflict with the proposed drainage channel for 114th Street from Slide Road to Quaker Avenue. Approximately 1,500 linear feet of 12-inch and 100 linear feet of 8-inch PVC pipe will be installed.
The net increase in contract price due to Change Order 2 is $284,562.00, with an increase in construction time of 60 days. The new contract amount is $9,277,768.02 and the new contract time is 600 days.
Fiscal Impact
Change Order No. 2 in the amount of $284,562.00, is funded in Capital Improvement Project 92750, Water Lines Ahead of Street Paving FY 2021.
Staff/Board Recommending
Erik Rejino, Assistant City Manager
Michael G. Keenum, P.E., Division Director of Engineering/City Engineer
Attachments
Resolution
Change Order No.2
Change_Order_No._1 (c)_Contract_16114_with_Lone_Star_-_Executed (4)
Original Contract_16114, Lone_Star_Dirt and Paving
Location Exhibit
Budget Detail
CIP Detail - 92669