- Amend Capital Improvement Project 8610, Remove and Reseal All Joints in Concrete by decreasing the appropriation and funding by $136,020, from $5,552,900 to $5,416,880. C.A.R.E.S Act funding will decrease $13,601, from $535,540 to $521,939 and the Airport Improvement Program (AIP) Grant will decrease by $122,419, from $4,819,860 to $4,697,441.
- Amend Capital Improvement Project 8648, Airfield Pavement Maintenance by the following change in funding: Airport Coronavirus Grant Program funding will decrease by $415,222 and the C.A.R.E.S Act funding will increase by $415,222. The total appropriation of the project will not change.
- Amend Capital Improvement Project 92579, Airport Property Improvements, by decreasing the appropriation and funding by $23,747, from $1,697,786 to $1,674,039. Funding changes are as follows: C.A.R.E.S Act funding will decrease by $47,120, from $1,557,625 to $1,510,505, Customer Facility Charge (CFC) Cash will increase by $23,373, from $0 to $23,373.
- Amend Capital Improvement Project 92675, Roof Repair and Replacement by decreasing the appropriation and funding by $2,053,718, from $2,513,215 to $459,497. C.A.R.E.S Act funding will decrease by $956,250, from $1,415,215 to $458,965, Airport Capital Cash will decrease by $1,097,468, from $1,097,468 to $0. The Airport Cash will be moved to 92859 Terminal Building – 2nd Floor Renovations.
- Amend Capital Improvement Project 92838, Airport Property Improvements by increasing the appropriation and funding by $112,281, from $150,000 to $262,281. C.A.R.E.S Act funding will increase by $27,255. CFC Cash will increase by 85,026, from $0 to $85,026.
- Amend the transfer from the CFC Fund to the Airport Capital Fund by $108,399, from $0 to $108,399.
- Establish Capital Improvement Project 92859, Terminal Building – 2nd Floor Renovations, and appropriate $1,097,468. The funding will be Airport Capital Cash moved from CIP 92675, Roof Repair and Replacement.
|