The scope of this project will include the replacement of a 408-foot segment of the Canyon Lakes Interceptor pipeline within the BNSF Railroad right-of-way, west of Aztlan Park. The pipe segment under the railroad can no longer adequately convey the wastewater flows, due to severe tuberculation of the ductile iron pipe. A new PVC pipe must be installed within steel casing under the BNSF Railroad. In response to RFP-21-15943-JM, two proposals were received on June 17, 2021.
Contractor |
Amount |
Utility Contractors of America, Inc., Lubbock, Texas |
$492,870 |
MH Civil Constructors, Inc., Amarillo, Texas |
$533,000 |
The proposals were evaluated using the following criteria: 60 points for Price, 20 points for Contractor Qualifications, 10 points for Safety Record, and 10 points for Construction Time. A four-member committee evaluated the Statements of Qualification and the following ranking was obtained.
Contractor |
Points |
Utility Contractors of America, Inc., Lubbock, Texas |
385.88 |
MH Civil Constructors, Inc., Amarillo, Texas |
358.92 |
Staff and the Evaluation Committee recommend award of the contract to the highest ranked contractor, Utility Contractors of America, Inc., of Lubbock, Texas, in the amount of $492,870. This contract is awarded by the unit price and actual expenditures may be more or less depending on field conditions. Time for substantial completion is 100 calendar days from the Notice to Proceed. |