AI# 12689
Regular City Council Meeting
6.14.2.
08/13/2024:
Information
Agenda Item
Resolution - Aviation:
Consider resolution authorizing the Mayor to execute Change Order No. 1 to Contract 17935, with Anthony Mechanical, Inc., for the Mechanical Equipment Replacement Project at Lubbock Preston Smith International Airport.
Item Summary
Change Order No. 1 consists of replacing 2 additional boilers and first time costs for payment and performance bonds. Due to the age and condition of the existing boilers and the lower than expected unit pricing for one replacement boiler, the airport has opted to begin phased replacement of the aging existing boilers.
The award of Alternate 2, along with the change order for 2 additional boilers, will allow for replacement of 3 of the 9 boilers.
The additional cost for the payment and performance bonds is a first cost item omitted from the original bid that does not affect the outcome of the bidding results.
Contractor - Anthony Mechanical, Inc., Lubbock, Texas
Cost
Unit Price of Alternate 2 ($80,500 per boiler X 2)
$161,000
Additional Costs for Payment & Performance Bonds
$3,220
TOTAL
$164,220
Airport Staff and the Airport Advisory Board recommend Change Order No. 1 be awarded to Anthony Mechanical, Inc. of Lubbock, Texas, for $164,220.
Fiscal Impact
Change Order No. 1 to Contract 17935 with Anthony Mechanical, Inc., for $164,220, is funded in Capital Improvement Project 92839, Mechanical Systems Improvements.
Staff/Board Recommending
Bill Howerton, Deputy City Manager
Kelly Campbell, Executive Director of Aviation
Airport Advisory Board
Attachments
Resolution - Change Order 1 Anthony Mechanical
Change Order #1 Anthony Mechanical
Capital Project 92839 Spreadsheet
CIP 92753-Detail
GO TO PREVIOUS PAGE
GO TO THE TOP OF THE PAGE
AgendaQuick ©2005 - 2026 Destiny Software Inc.
All Rights Reserved.