AI# 12775
Regular City Council Meeting
6.11.
08/13/2024:
Information
Agenda Item
Resolution - Engineering:
Consider a resolution authorizing the Mayor to execute Public Works Contract 18109, with Winston Electric Inc., dba Acme Electric Company, Texas, for the West Lubbock Water System Expansion early procurement.
Item Summary
The City will need major infrastructure upgrades to maintain an appropriate level of service to West Lubbock, including a new pump station, ground storage tank (GST), elevated storage tank (EST), and transmission pipelines. All of this infrastructure is necessary together in order to maintain the Texas Commission on Environmental Quality (TCEQ)minimum requirements in the west Lubbock area in the near future.
In order to expedite the West Lubbock Pump Station Project, City staff recommends procuring longer lead time items ahead of the pump station bid. An Invitation to Bid (IBT) was issued to supply the electrical equipment needed for the new pump station in West Lubbock, including a generator, switchboards, Variable Frequency Drives (VFD), and other long lead-time equipment.
In response to ITB 24-18109-KM, the following bids were received and opened on June 25, 2024.
Contractor
Amount
***The Reynolds Company, Fort Worth, Texas
$397,500
Winston Electric, Inc. dba Acme Electric Company, Lubbock, Texas
$2,449,900
***The Reynolds Company’s bid did not include a generator, enclosures, or an Automatic Transfer Switch. Due to their choice to not submit a bid on these critical path lead-time items, their bid was not considered.
Staff recommends award to the lowest responsible bidder, Winston Electric, Inc. dba Acme Electric Company of Lubbock, Tx, for $2,449,900.
The contract will be for a term of 700 consecutive calendar days with final completion of the project within 730 consecutive calendar days. The equipment will be stored by the contractor upon delivery and installed with the construction of the proposed new pump station.
Fiscal Impact
This contract for $2,449,900, is funded in Capital Improvement Project 92806, West Lubbock Water System Expansion.
Staff/Board Recommending
Erik Rejino, Assistant City Manager
Michael G. Keenum, PE, Division Director of Engineering/City Engineer
Attachments
Resolution
Contract
Location Map
CIP Spreadsheet
CIP Detail
Project Summary Sheet
GO TO PREVIOUS PAGE
GO TO THE TOP OF THE PAGE
AgendaQuick ©2005 - 2026 Destiny Software Inc.
All Rights Reserved.