Resolution - Engineering:
Consider a resolution authorizing the Mayor to execute Amendment No. 1 to Professional Services Agreement Contract 14868, with Provenance Engineering, LLC, for professional engineering services associated with the construction of the Lift Station 31 Force Main Rehabilitation Project.
Item Summary
The purpose of this project is to install a new 14-inch PVC sanitary sewer force main to transport flow from Lift Station 31 to the 34th Street Sanitary Sewer Interceptor. This project will replace the existing 14-inch ductile iron force main under Quaker Avenue that has serviced Lift Station 31 since the 1950’s. Amendment No. 1 to Contract 14868 will provide Professional Engineering services associated with the construction of the Lift Station 31 Force Main Rehabilitation Project.
Fiscal Impact
This amendment for $23,800 is funded in Capital Improvement Project 92446, Sewer Line Replacement.
Staff/Board Recommending
Jesica McEachern, Assistant City Manager
Attachments
Resolution - Amendment 1 to Contract 14868
Amendment 1 to Contract 14868
Original Contract 14868
Location Exhibit
Budget Detail
CIP Detail
AgendaQuick ©2005 - 2024 Destiny Software Inc.
All Rights Reserved.