Consider a resolution authorizing the Mayor to execute Public Works Contract 18195, with Trifecta Services Company, for the demolition and removal of a water tower at 74th Street and Genoa Avenue.
Item Summary
This project’s purpose is to de-commission and dismantle elevated and ground storage tanks that were replaced by newly constructed elevated and ground storage tanks.
In response to ITB 24-18195-KM, the following bids were received and opened on August 12, 2024.
Contractor
Amount
Trifecta Services Company, Pflugerville, Texas
$135,000
Hunter Demolition & Wrecking Corp, Bexar, Texas
$156,500
Veit National Corporation, Hennepin, Minnesota
$281,510
Intercon Demolition, Lubbock, Texas
$305,000
Staff recommends award to the lowest bidder, Trifecta Services Company of Pflugerville, Texas, for $135,000.
The contract will be for a term of 210 calendar days from the date of the Notice to Proceed, with liquidated damages of $300 per day for each day that substantial completion exceeds the 180-day limit, and $100 per day of liquidated damages for each day that final completion exceeds the 210-day limit.
Fiscal Impact
Contract No. 18195 for $135,000 is funded in Capital Improvements Project 8687, Demo of Elevated and Ground Storage Tanks.
Staff/Board Recommending
Erik Rejino, Assistant City Manager
Bailey Ratcliffe, P.E., Interim Division Director of Engineering/City Engineer
Attachments
Resolution
Contract
Location Exhibit
CIP Spreadsheet
Budget Detail
Project Summary
AgendaQuick ©2005 - 2025 Destiny Software Inc.
All Rights Reserved.