ITEM 22 |
City Council Memorandum Public Works & Utilities Memo No. CP22-173
|
Date: |
May 26, 2022 |
To: |
Mayor and Council |
Thru: |
Joshua H. Wright, City Manager Andy Bass, Deputy City Manager John Knudson, Public Works and Utilities Director Kimberly Moon, Acting Capital Projects Manager |
From: |
Vivianna Barrientes, Engineering Project Manager |
Subject: |
Construction Manager at Risk Contract No. ST2009.401, Change Order No. 1, with DCS Contracting, Inc., for the Dobson Road Improvements at Intel Driveways #1 and #4 - GMP No. 2 |
|
|
|