Resolution - Aviation: Consider a resolution authorizing the Mayor to execute Public Works Contract 15877, with Silver Creek Construction, Inc., for the rehabilitation of Airport Taxiway M and Taxiway J at Lubbock Preston Smith International Airport.
Item Summary
Silver Creek Construction, Inc. will remove and replace failed concrete panels, and perform concrete spall repair, crack seal, joint seal, and joint beveling on Airport Taxiways M and Taxiway J.
In response to ITB 21-15877-, bids were received from the following contractors.
Company
Amount
Silver Creek Construction, Inc., Ponder, Texas
$599,700.00
Hensel Phelps Construction Company, Austin, Texas
$662,254.51
The contract is awarded by the unit price. The total amount of the award is based on expected quantities and actual expenditures may be more or less depending on actual quantities installed. The price per unit will not change.
Airport staff and Airport Advisory Board recommend contract award to the lowest bidder, Silver Creek Construction, Inc. of Ponder, Texas. Time for completion is 100 calendar days.
Fiscal Impact
Contract 15877 with Silver Creek Construction is for $599,700.00 and is funded through Capital Improvement Project 8648 Airport Pavement Maintenance.