Consent 1.A.5.
Regular City Council Meeting
- Meeting Date:
- 05/27/2014
- TITLE
- Bid Award for the Airport Ramp Rehabilitation Project
- PRESENTED BY:
- Tom Binford
- Department:
- Airport
Presentation:
PROBLEM/ISSUE STATEMENT
Included in the Airport's Capital Improvement Program is the Airport Ramp Rehabilitation project. The eligible portion of this project will be funded 90% with a Federal Aviation Administration (FAA) Airport Improvement Program (AIP) grant and the balance with local funds. The project will rehabilitate 27,000 square feet of the 20-year-old deteriorating asphalt ramp adjacent to the air carrier apron. The project will remove the old asphalt pavement and aggregate sub-base, and replace it with 21 inches of new base and 5 inches of new asphalt to provide the strength to accommodate large aircraft. The project also includes maintenance repairs to Runway 7/25 for some abnormally large lateral asphalt cracks, the cost of which will be paid 100% with local funds. The project was advertised in the Billings Times on April 24, May 1 and 8, and was posted on the City's Website. On Tuesday, May 13, 2014, the following bids for this project were received.
| CONTRACTOR | TOTAL BID |
| Knife River | $1,037,810.20 |
| JEM | $1,229,287.00 |
ALTERNATIVES ANALYZED
The City Council may:
- Approve the bid award for the Airport Ramp Rehabilitation Project; or
- Decline the bid award, reject all bids, and delay the project.
FINANCIAL IMPACT
The total cost of this project is $1,037,810.20. The eligible portion of the project funded with the FAA AIP grant is $986,201.20. The 90% Federal portion of the eligible costs is $887,581.08 and the remaining balance of the project's costs totals $150,229.12, and will be paid with local funds.
RECOMMENDATION
Staff recommends the City Council approve the award of this project to the low bidder, Knife River, for the amount of $1,037,810.20.
APPROVED BY CITY ADMINISTRATOR