Consent 1.A.1.
Regular City Council Meeting
- Meeting Date:
- 01/28/2013
- TITLE
- Bid Award: W.O. 13-03 #1 City Overlay
- PRESENTED BY:
- David Mumford
- Department:
- Public Works
Presentation:
Information
PROBLEM/ISSUE STATEMENT
Staff opened bids on January 22, 2013, for the 2013 Street Maintenance Program, City Overlay Contract. This project is part of the on-going Street Preventative Maintenance Program supported by the City Council since 1985. Annually, staff identifies streets proposed for preventative maintenance. Staff bids this work in three contracts: chip seal resurfacing, overlay resurfacing and crack sealing. This contract will provide an overlay on approximately 3 miles of streets throughout the City. In order to allow staff additional time to review the bids, the results will be presented for award recommendation at the February 11, 2013 City Council meeting.
ALTERNATIVES ANALYZED
The Council may:
• Delay award of Work Order 13-03 #1 City Overlay until the February 11 City Council meeting; or
• Reject all bids and not award Work Order 13-03 #1 City Overlay.
• Delay award of Work Order 13-03 #1 City Overlay until the February 11 City Council meeting; or
• Reject all bids and not award Work Order 13-03 #1 City Overlay.
FINANCIAL IMPACT
Funding for Work Order 13-03 #1 City Overlay is included in the FY13 budget. The project was bid on January 22 and the results of that bid will be presented for award recommendation at the February 11, 2013 City Council meeting.
RECOMMENDATION
Staff recommends that Council delay award of a construction contract for Work Order 13-03 #1 City Overlay until the February 11, 2013, Council meeting to give staff time to review the bids.
APPROVED BY CITY ADMINISTRATOR
Attachments