Consent 1.A.4.
Regular City Council Meeting
- Meeting Date:
- 04/09/2018
- TITLE
- Bid Award: W.O. 18-04; 2018 ADA Ramp Replacement Project
- PRESENTED BY:
- David Mumford
- Department:
- Public Works
Presentation:
No
PROBLEM/ISSUE STATEMENT
W.O. 18-04, 2018 ADA Ramp Replacement Project, is a project consisting of Americans with Disabilities Act (ADA) accessible ramp construction on the street corners where the City will soon be completing pavement overlays and chip seals and on other corners at various locations throughout Billings.
The annual ramp construction project is in accordance with the City’s agreement with the Department of Justice to install/upgrade ramps along streets constructed or reconstructed after 1992 and in specific areas identified by need. The miscellaneous ramp locations were selected based upon neighborhood requests.
The project was advertised on March 9th,16th, and 23rd, 2018 on the City's Website and in Yellowstone County News. Bids were opened on March 27th, 2018 and five bids were received. J&J Concrete, Inc. submitted the lowest responsible bid.
The annual ramp construction project is in accordance with the City’s agreement with the Department of Justice to install/upgrade ramps along streets constructed or reconstructed after 1992 and in specific areas identified by need. The miscellaneous ramp locations were selected based upon neighborhood requests.
The project was advertised on March 9th,16th, and 23rd, 2018 on the City's Website and in Yellowstone County News. Bids were opened on March 27th, 2018 and five bids were received. J&J Concrete, Inc. submitted the lowest responsible bid.
ALTERNATIVES ANALYZED
The Council may:
- Award Work Order 18-04, 2018 ADA Ramp Replacement Project to J&J Concrete, Inc. in the amount of $92,640; or
- Do not award Work Order 18-04. If not awarded, the City would need to re-bid or cancel the project and construct the ramps in a subsequent year.
FINANCIAL IMPACT
The following bids were received and evaluated:
The funding for this project is included in the approved budget for fiscal year 2018. Gas Tax funds will be used for this project.
| Contractor | Total Bid |
| J&J Concrete, Inc. | $92,640 |
| American Concrete | $105,253 |
| CMG Construction, Inc. | $117,295 |
| EHC, LLC | $122,833.50 |
| Askin Construction, Inc. | $153,567 |
The funding for this project is included in the approved budget for fiscal year 2018. Gas Tax funds will be used for this project.
| Budget | $110,000 |
| Previously Encumbered | $0 |
| This contract | $92,640 |
| Remaining Budget | $7,360 |
RECOMMENDATION
Staff recommends that Council award W.O. 18-04, 2018 ADA Ramp Replacement Project to J&J Concrete, Inc. in the amount of $92,640.