- Approve an increase to contract IFB 10-66-HFP-04 Emulsified Asphalt Products
- Submitted By:
- Terry Hudson, Procurement
- Department:
- Procurement
Presentation:
No A/V Presentation
Recommendation:
Approve
Document Signatures:
BOS Signature NOT Required
# of ORIGINALS
Submitted for Signature:
Submitted for Signature:
0
NAME
of PRESENTER:
of PRESENTER:
Terry Hudson
TITLE
of PRESENTER:
of PRESENTER:
Procurement Director
Mandated Function?:
Not Mandated
Source of Mandate
or Basis for Support?:
or Basis for Support?:
Docket Number (If applicable):
Information
Agenda Item Text:
Approve an increase for Contract No. IFB 10-66-HFP-04 with Western Emulsions, Inc. in the not to exceed amount of $500,000 for emulsified asphalt products for the period of August 1, 2014 through July 31, 2015.
Background:
On July 8, 2014, the Board of Supervisors approved the renewal of Contract No. IFB 10-66-HFP-04 for the purchase of CRS-2 and CRS-2P emulsified asphalt products for the period of August 1, 2014 through July 31, 2015. An additional amount of $500,000 is required to complete the FY14/15 work plan and IGA projects.
Department's Next Steps (if approved):
Process a change order to the existing contract and monitor contract performance.
Impact of NOT Approving/Alternatives:
These projects will be delayed until a new contract is approved by the Board of Supervisors.
To BOS Staff: Document Disposition/Follow-Up:
No action required.
Fiscal Impact
- Fiscal Year:
- One-time Fixed Costs? ($$$):
- Ongoing Costs? ($$$):
- County Match Required? ($$$):
- A-87 Overhead Amt? (Co. Cost Allocation $$$):
- Source of Funding?:
Fiscal Impact & Funding Sources (if known):
The Community Developement, Highway and Floodplain Division has budgeted for these expenditures in fund line 251-4010-9-413.700.