Action 13.
Regular Board of Supervisors Meeting
Facilities
- Meeting Date:
- 01/23/2024
- Title:
- Construction of New Facilities Maintenance Building and Utility Trenching
- Submitted By:
- Jackie McElyea, Facilities
- Department:
- Facilities
Presentation:
No A/V Presentation
Recommendation:
Approve
Document Signatures:
BOS Signature Required
# of ORIGINALS
Submitted for Signature:
Submitted for Signature:
1
NAME
of PRESENTER:
of PRESENTER:
Darrel Crowley
TITLE
of PRESENTER:
of PRESENTER:
Facilities Interim Director
Mandated Function?:
Not Mandated
Source of Mandate
or Basis for Support?:
or Basis for Support?:
Docket Number (If applicable):
Information
Agenda Item Text:
Approve Contract 23-01-FAC-01 with KWR Construction for the construction of a Facilities maintenance building in the amount of $2,753,551.55 and approve Proposal with KE&G for utility trenching in the amount of $123,598.00 at parcel 102-30-114W, 1228 Hereford Rd. Bisbee, AZ 85603, effective January 23, 2024.
Background:
The Facilities Management Department worked with Procurement in issuing requirements for the construction of the Facilities Maintenance Building through the formal bidding process. The Procurement Department issued Request for Proposal 23-01-FAC-01 with a deadline of February 10, 2023. All bidding vendors attended a site visit. All proposals were reviewed with the winning bidder being KWR Construction.
KE&G will do the utility trenching under City of Tucson Contract #171729.
KE&G will do the utility trenching under City of Tucson Contract #171729.
Department's Next Steps (if approved):
If approved, issue purchase orders to KWR Construction and KE&G and schedule the work.
Impact of NOT Approving/Alternatives:
The Facilities maintenance building would not be constructed and utilities would not be established.
To BOS Staff: Document Disposition/Follow-Up:
Please send the signed, original copies to Jackie McElyea and (1) copy to Anne Coppola in Procurement.
Fiscal Impact
- Fiscal Year:
- 23/24
Fiscal Impact & Funding Sources (if known):
Funding will come out of Construction/Capital for FY 23/24.
Attachments
- Acceptance Award Letter
- Vendor Response Cover Letter
- KWR Proposal
- Scope of Work
- Structural and Architectural Design Narrative
- Electrical Design Narrative
- Mechanical Design Narrative
- Invitation for Bid
- KWR SOW Narrative
- KWR Past Performance
- KE&G Contract - City of Tucson
- KWR PAST Proposal
- KE&G Proposal